Development Timeline

  • January 2017

    antique-classic-close-up-2263062 Planning application submitted
  • July 2017

    approved-29149_1280 Planning permission granted with conditions. Conditions were sucessfully met and discharged November 2018.
  • June 2019

    IMG_0416 2 IAE appoint Collins Earthworks Ltd as main contractor for phase 1 ground improvement works.
  • July 2019

    IMG_03722 The first machines arrive on site
  • July 2019

    DCIM100MEDIADJI_0013.JPG The first cut is made and ground modification works commence
  • August 2019

    IMG_1141 2 The 1st of 3 mine shafts on the development located, treated and grout capped