January 2017
Planning application submitted -
July 2017
Planning permission granted with conditions. Conditions were sucessfully met and discharged November 2018. -
June 2019
IAE appoint Collins Earthworks Ltd and Blue Earth Construction Ltd as preferred contractors. -
July 2019
The first machines arrive on site. -
July 2019
The first cut is made and ground modification works commence. -
August 2019
The 1st of 3 mine shafts on the development located, treated and grout capped. -
September 2019
Excavation works commence exposing two mine shafts ready to cast a concrete cap on top of each shaft. Also, sheet piles are installed to stabilise the ground and form the new access ramp connecting our existing site to the new site. -
October 2019
Following the capping of 2 mine shafts, the excavation was backfilled and ground stabilised. -
November 2019
Drainage works in preparation for the southern access road is completed. Phase 1 of the perimeter Zebex security fencing is installed. Drainage and kerbs are installed on the access road between the existing site and the new site. -
December 2019
Drainage and kerbs on the access road are completed and road base prepared for concrete in the new year. -
January 2020
The first concrete pour on-site begins on the newly constructed main access ramp. -
February 2020
Excavation and installation of water attenuation tubosider. -
March 2020
Last concrete pours of phase 1 are completed before construction is paused due to the Coronavirus pandemic. Work, however, continues off-site with an additional planning application submitted to further expand the site. -
August 2020
Contractors return to site after a pause in on-site works due to the Coronavirus pandemic. Drains are brought up to level and connections made. -
September 2020
The final sections of tubosider pipes are installed completing the rainwater attenuation installation. -
October 2020
With the tubosider pipes in place, they are covered up and ground made good ready for concrete preparation. -
January 2021
BlueEarth Construction Ltd is awarded the contract to build the first phase of the development consisting of a 156m x 50m (7,800m2 - 84,000ft2) production area (MFP4), in-house demonstration and learning centre (3,600m2 - 39,000ft2). In total this phase will create an additional 123,000ft2 of internal floor space and 116,000ft2 of external storage area. -
March 2021
Concrete is poured to form the remaining phase of the 116,000ft2 external storage area. -
May 2021
Piling rigs arrives on site, which are used to drive 12m piles into the ground to a depth of 20m, creating a stable base for us to build upon. -
August 2021
Steel arrives on site for the main superstructure